Saturday, February 12, 2011

Rear bedroom

The rear bedroom walls are down, I've shown the progress starting with what was originally there:







After we removed all the walls and floors, we raised the roof 3 ft. We did this with a series of 20 ton jacks, some 4x4 posts over about a week. I was a bit terrified that something was going to snap and the roof would cave in. Nonetheless, we're done with raising the roof.
Front elevation, showing the original angle of the rear addition roof.

Front elevation, showing the new angle of the rear addition roof. The angle mirrors the Living Room roof angle, giving the house a "Butterfly roof".


Rebar epoxied into the old foundation. Ready for the pour.